Self Build Timeline for a Dublin Smart Home: What Happens at Each Stage

Crystal chandelier lighting a curved stairwell, the finished result of a self build timeline that fixed the lighting positions early

On a self build timeline, the smart home decisions come much earlier than most people expect: the comms cabinet and the cable routes belong on the drawings before the electrical tender, and every cable has to be in the walls before the plasterers arrive. If you work through the stages in order, from planning to handover, the technology is finished on the same day as the house instead of being squeezed in afterwards. This guide sets out what happens at each stage of a Dublin self build and what you need to decide before each one.

It is written for people building their own home in and around Dublin, from a replacement house in Howth or Killiney to a one off house near Rush, Lusk or Garristown. The order of works is much the same on every site. What changes is how early you start thinking about the network, the lighting and the rest, and that is the part a self builder controls.

The self build timeline at a glance

The table shows the main stages of a typical build and what the smart home side needs at each one. Your own programme will move around, but the order rarely changes.

Stage of the build What the smart home needs Who is involved
Design and planning A list of the systems you want and a space for the comms cabinet on the plans You and your architect
Before commencement and tender Device positions, a cable schedule and a budget, so the electrical quotes match You, the architect, us
Groundworks Ducts from the road for broadband and out to the garden, gate and any outbuildings The groundworker, guided by our drawings
Weathertight shell A walk round to confirm positions on site, including window and blind heads You, the electrician, us
First fix Every data, speaker, keypad and sensor cable run, labelled and tested The electrician, with us on hand
Plastering and finishes Cables protected, nothing new can be added without chasing The plasterer and the other trades
Second fix Keypads, speakers, access points, screens and the rack fitted The electrician and us
Commissioning and handover Scenes programmed, everything tested, drawings and logins handed over Us, with you

Design and planning: decide what you want

At this point you do not need to choose a single product. You need a short list of the systems you want in the house: good Wi-Fi in every room, lighting control, music, a television in the main rooms, an alarm and cameras, heating controls, perhaps motorised blinds or an electric gate. That list is enough for the architect to leave room for a comms cabinet, ideally a ventilated cupboard near the centre of the house rather than a corner of the garage.

It also helps to think about how you will live in the house. Which door will you use every day? Where will the children do homework? Will you work from home? Those answers decide where the keypads, the data points and the access points go, and they are much easier to change on paper than on site.

Before commencement: get the design pack done

Before building work can start, the owner lodges a Commencement Notice with the local building control authority. The Government's Commencement Notices page on gov.ie explains that these notices are submitted through the national online Building Control Management System (BCMS), and that a person building a single house on a development site can lodge a commencement notice with an opt out declaration, choosing not to use statutory certification. Whichever route you take, the house must still meet the Building Regulations, so good drawings matter even more.

This is also the right time to finish the smart home design, because you are about to ask electricians for prices. With a numbered set of device positions and a cable schedule in hand, every quote is for the same scope. Our post on what a smart home design pack includes explains the drawings we produce through our survey and design service, and the smart home cost guide helps you set a budget before you tender.

Groundworks: the ducts nobody remembers

The first trench on site is the moment to lay ducts, and it is the stage most often missed. A duct from the boundary to the house is needed for fibre broadband, and while the digger is there it costs very little to add ducts to the gate pier, the garden lighting, outdoor speakers and any garage or garden room. Our guide to fibre broadband for a Dublin self build covers the broadband duct in detail.

Leave a draw rope in every duct and mark the ends clearly. Once the drive is surfaced and the lawn is laid, an extra cable means digging it all up again.

Weathertight shell: walk the house before first fix

Once the roof is on and the windows are in, the rooms finally have their real size and light. This is the best time for a site walk with you, the electrician and us. We mark the positions from the drawings on the walls and ceilings, check them against the joists and the window heads, and agree any changes before a single cable is pulled. If you are planning motorised blinds or curtains, the pelmet and window head details need to be agreed with the window supplier now.

First fix: everything goes in the walls

First fix is the busiest stage of the whole self build timeline for the smart home. The electrician runs the mains cabling and, from our cable schedule, every Cat6 data cable, speaker cable, keypad cable and sensor cable back to the comms cabinet. Each cable is labelled at both ends with its number from the schedule, so it can be found years later.

Our founder, Kieran McGuire, is an electrician, and so are a few of our team, so we understand the pressure on site at this stage. We stay in contact with your electrician through first fix and answer questions as they come up. Our first fix wiring guide lists what has to be in the walls, and our post on why your smart home installer should also be an electrician explains how the two jobs fit together.

Before the plasterers start, check these off:

  • Every line of the cable schedule ticked as installed and labelled at both ends.
  • Data cables tested, so a damaged cable is found while it can still be replaced.
  • Back boxes at the agreed heights for keypads, touch screens and intercoms.
  • Ceiling speaker and access point positions clear of joists, lights and fire stopping.
  • Photographs of every wall and ceiling taken before it is boarded.

Second fix, commissioning and handover

After the painters, the electrician fits the sockets and switches and we fit the keypads, speakers, access points, cameras and touch screens, then build the rack in the comms cabinet. Commissioning is where the house comes to life: lighting scenes are set room by room, the heating, blinds and audio are linked, and the Wi-Fi is tested in every room and out in the garden. For lighting, our lighting control page for Dublin shows the systems we install.

At handover we walk you through the system, give you the logins and leave the final drawings and cable schedule with the house. Move in with a little time to spare: a week of living in the house usually turns up a few scene names or timings you want changed.

Questions we are often asked

When is the latest we can bring in a smart home company?

Before first fix, but that is late. The best time is while the drawings are being finalised, so the comms cabinet has a home and the electrical quotes include everything.

Does the smart home add time to the build?

Very little, if it is planned. The cables go in during first fix alongside the mains wiring, and the fitting and programming happen alongside the painters and the other second fix trades.

We have already started. Is it too late?

Not while the walls and ceilings are still open. If the house is already plastered, we design around what is there, using wireless products where cables cannot reach.

What does it cost to get started?

A consultation or site survey is €440 plus VAT covering up to 4 hours, and extra time is €110 an hour plus VAT.

Who looks after the system once we move in?

We do, if you want us to. Because the drawings and cable schedule stay with the house, any engineer can also see how it was built.

The network is the easiest place to start, because almost everything else in the house depends on it. Send us your floor plans and we will mark the Wi-Fi access points, list the Cat6 runs back to one comms cabinet and send you a priced kit list, free and with no obligation. Our free Wi-Fi design for self builders explains how to send them, and our process page shows what happens next.

Book a consultation or call our Dublin office on 01 906 9326.